August 15, 2003  
 

 

Fiscal Year-End Procurement Dates

Please consider the following dates and dollar amounts if you are planning to submit a requisition that needs to be delivered and accepted before the end of FY03 (September 30, 2003).

Requisitions must be entered into PeopleSoft on or before these dates:

Friday, August 22
Requisitions for $101,000 and over

Friday, September 5
Requisitions for $25,000 - $100,000

Thursday, September 18
Requisitions for less than $25,000

Any purchase requisitions entered into PeopleSoft after these dates will be processed with a delivery date of October 1 or later.

Contact: Janet Adams, Purchasing Office, Ext. 8515, jadams@slac.stanford.edu

 

The Stanford Linear Accelerator Center is managed by Stanford University for the US Department of Energy

Last update Wednesday August 13, 2003 by Kathy B