LCLS Construction Update
By David Saenz
There are currently four LCLS
projects under construction:
Sector 20 Injector Facility
The 1,600 square foot Alcove that
had been utilized over the years as a
Pump Repair Room and Mechanical
Shop for the plant engineering staff
has been demolished. The LCLS
project will use this space for a new
2,000 square foot facility to house
the Laser Injector and RF Gun.
Steel erection will commence in
November with a final construction
scheduled completion date at the
end of February 2006. Due to the
construction activities, north access
along the gallery will continue to
be limited access. The LCLS Project
Manager is Bob Law.
Magnetic Measurement Facility
(MMF)
The interim home for the undulators
(MMF) is scheduled for completion
by late February 2006. This facility
will be located in the existing
Bldg. 81 and will contain the new
undulators being provided by the
Advanced Photon Source at ANL.
These components will require fine
tuning and calibration before they
are relocated to the Undulator Hall
in May 2007. The majority of the
demolition is complete and new
concrete foundations have been
poured. The LCLS Project Manager
is Javier Sevilla.
Sector 24 Equipment Access
What was previously an empty 35-
foot concrete shaft now has a set of
steel stairs. These stairs are designed
for easy removal should equipment
need to be lowered into the shaft.
The facility also includes a new metal
enclosure to allow for ease of access.
The LCLS Project Manager is Jesse
Saldivar.
FFTB/RSY Vertical Exterior
Shielding
A total of 12 exterior shielding
blocks have been removed. Each
9’x 9’x 3’concrete block is a 19-ton
load. These have been replaced
with a concrete plug of similar
thickness. Removal of the blocks
was scheduled at this time so that
radiation protection remains in place
until FFTB demolition is completed.
The LCLS Project Manager is Jesse
Saldivar.
Major Construction to Begin in
March 2006
The major phase of LCLS
construction is scheduled to begin
in March 2006 with possibly some
site work beginning earlier. The full
design will be completed by Jacobs
Engineering in January 2006. The
construction phase will be managed
by Turner Construction. The new
Beam Transport Hall (BTH) facility
will stretch across the Research Yard,
bisecting the area.
The FFTB structure in the Research
Yard is scheduled for demolition
next year. Other buildings that will
be required for demolition include
buildings 102A, a portion of building
102B and the High-Bay of Bldg. 113.
During all the construction activities
safety will be paramount for
contractors and lab employees.
Watch for Web Cams
For those who want to keep close tabs on progress during the major
construction phase, watch for news and views from the web cams which
will be going up in the Research Yard.